BIM Goals & Uses
Define project-specific BIM objectives and intended digital uses.
Define how BIM will actually be delivered on the project — including BIM uses, team responsibilities, model structure, LOD and LOI, coordination procedures, information exchanges, QA requirements and digital handover expectations.
A project may require BIM, but that requirement alone does not define how different teams should work together.
The BIM Execution Plan converts high-level digital requirements into project-specific procedures for modeling, coordination, information exchange, quality control and delivery.
It provides the practical operating framework that connects BIM expectations with day-to-day project execution.
The level of detail within a BEP should match project complexity, procurement strategy, BIM requirements and delivery stage.
Define project-specific BIM objectives and intended digital uses.
Clarify responsibilities for model creation, review, coordination and information delivery.
Define project models by discipline, building, zone, package or delivery need.
Establish required geometry and information development at defined project stages.
Define naming, structure, reference and model conventions.
Establish project origin, reference and federation expectations.
Define federation, test structure, issue assignment and closure workflow.
Define required model and data exchanges at project milestones.
Establish checks required before information is issued or accepted.
Coordination becomes difficult when multiple teams assume someone else owns a model element, interface or decision.
The purpose of a BEP is not to create a long document that sits unused.
It should create practical rules that project teams can apply consistently throughout delivery.
Review project BIM requirements, scopes and delivery objectives.
Establish BIM uses, deliverables, development levels and project roles.
Define models, naming, coordinates and information exchanges.
Establish federation, clash review and issue-management procedures.
Define QA gates, review criteria and delivery checks.
Update the BEP when approved project requirements materially change.
Define naming conventions for models, drawings, exports and other digital deliverables.
Establish consistent discipline, building, zone or package identifiers.
Define project-specific view and sheet naming where required.
Define origin, shared references and federation alignment.
Establish project expectations for reference geometry used across disciplines.
Define data fields required for project-specific information uses.
Define when project models should be divided by building, zone, level or package.
Define required native, federated or project-defined exchange outputs.
The BEP can define how files and models move through the project's chosen information environment.
A project team should not need to invent acceptance criteria each time a model is delivered.
The BEP can establish repeatable checks for model readiness, coordination and information delivery.
The BIM Execution Plan can define workflows, information requirements, responsibilities and coordination processes.
It does not independently change contractual design authority, professional engineering responsibility, code obligations or formal project approvals unless those matters are addressed through the appropriate contractual process.
A BIM Execution Plan defines how project BIM requirements will be implemented through modeling, coordination, information exchange, quality control and digital delivery procedures.
BIM execution planning is most useful when developed early enough to guide project mobilization, modeling and coordination workflows. It may then be updated as approved project requirements evolve.
Yes. The plan can define project-stage requirements for model geometry and project information based on intended BIM uses.
Yes. The BEP can define required discipline interfaces, clash-testing expectations, review responsibilities and issue-closure procedures.
Yes. Project-specific file states, revision control, information exchange and approval workflows can be documented for the selected environment.
No. A BEP supports project BIM execution and information management. Contractual authority, professional responsibility and formal approvals remain subject to the project's agreements and responsible parties.
Share your BIM requirements, project team structure, required BIM uses, coordination expectations and digital delivery milestones.